THE SCHEDULE!!! Sticky

A topic by Evan Connolly created Jan 06, 2025 Views: 35
Viewing posts 1 to 1
Developer (1 edit)

20 Jan - 17 Feb (x5 Weeks)

Design, Print and Distribute Workbooks

This needs to be done first so the test audience has time to fill out the workbook

24 Feb - 21 Apr (x9 Weeks)

Develop Video Game

I believe this will be the largest workload of the project, so I'm allotting a lot of time, 
This will also give the test audience plenty of time to complete the workbooks.

28 Apr - 12 Mar (x3 Weeks)

Collect workbooks, Design & Print Art Book

Test audience will have most of the work done for me, I'll just have to put it all together and make it look nice.